ISCIR authorisation assembly and repair of lifting equipment

ISCIR authorisation maintenance and revision of lifting equipment

A. Documents necessary for tower/trolley hydraulic cranes

Issuance of the approval for the commencement of the assembly works
-assembly plan endorsed by RADTP
-technical memorandum (engineer or non-beneficiary) endorsed by RADTP
-geotechnical survey
-topometry sheet (in case that the crane is on the railway track
-earth socket certificate

ALL ABOVE DOCUMENTS SHALL BE FILED WITH ISCIR 30 DAYS AHEAD

B. Technical verification in use

-SCIR approval for commencement of assembly works
-assembly design endorsed by RADTP
-plan with the safety places (If not included in the design)
-operational test report – signed by the beneficiary as well
-conformity declaration for assembly
-topometry sheet – containing achieved levels
-earth socket certificate
-conformity declaration for execution of the foundation or railway track
-STEEL quality certificate – foundation reinforcement
-CONCRETE quality certificate – foundation